A24: Roviano landslide highway section reopens to dual lanes in both directions

Just two weeks after the rockfall on the A24 highway near Roviano, the section affected by the landslide has been reopened to dual lanes in both directions. A result achieved, working day and night, by Toto Group technicians, in coordination with SdP staff, who installed a special rockfall barrier in time for the long Easter weekend. Once again, group synergies made it possible to remedy a dangerous situation on a section of the highway, the one between the Carsoli/Oricola and Vicovaro/Mandela exits, which was designed and built in a landslide area more than half a century ago and should be rebuilt as a variant, as endlessly represented to the granting Ministry.

To reopen the highway, SdP took immediate action with a temporary solution, a concrete wall installed in just 30 hours, which made it possible to buffer the emergency and reopen to traffic in both directions, albeit on only one lane. Now a special rockfall net has made it possible to restore full traffic flow on both carriageways. The net, with an extension of 60 meters and a height of 6 meters, has been tested to absorb up to 5,000 kJ thanks to a device to dissipate the energy produced by landslides. It was safely installed by experienced rock climbers in constant coordination with operators who monitored signs of further detachments upstream in real time.

Uprights will be installed to extend the rockfall barrier for another 100 meters upstream and downstream of the landslide area, where the danger is not immediate but must be prevented. Work will be suspended to allow full safe use of the highway over the Easter period. They will resume from Tuesday, April 19, with possible roadway reductions and full reopenings on weekends.

SdP once again moved first and alone, in a climate of constant emergency, because the economic planning tool that regulates the relationship between Concessionaire and Grantor and indicates priority interventions, the PEF, has been missing for almost 10 years. Waiting for approval, after 18 projects and simulations sent by SdP to the relevant ministries, the section between Carsoli and Vicovaro, which has reached the end of its life, had recently been included by the Extraordinary Commissioner in the list of the most urgent projects, for which the first 800 million euros are already available. But bureaucracy delays the opening of the construction site for the variant section, deaf and impassive in the face of all the signs reminding us that time has already run out.

The Web TV of Strada dei Parchi

Web TV

Lavori e Sicurezza

Infrarob, the “pothole capping rover” for infrastructure maintenance

Let’s learn about InfraROB, the experimental project that marks a breakthrough in innovation applied to infrastructure maintenance. InfraROB is a prototype autonomous robot developed as part of...

Recent news

WEEKEND

With A24 and A25 in the hidden places of the FAI Autumn Days

On Saturday, October 11 and Sunday, October 12, the FAI Fall Days return to unveil an extraordinary heritage of 700 inaccessible or little-valued places that are usually unvisited, little known and...

SAFETY

Defibrillators on highways: A24 and A25 become cardioprotected

Strada dei Parchi has launched a crucial initiative for the health and safety of highway users to make the service areas of the A24 and A25 highways cardioprotected, able to deal with cardiac...