The route passes through one of the areas of the central Apennines most exposed to seismic risk. The A24 and A25 highways are also recognized as strategic infrastructure for Civil Protection purposes (Law 228/2012), as they provide a connection between Rome, the inland areas affected by earthquakes, and the Adriatic coast.
The original viaducts were designed and built in the 1960s, according to technical standards that predated the most recent regulations on structural safety and seismic behavior.
Between L’Aquila Ovest and Tornimparte, “strada dei parchi” is completing a major project to demolish and rebuild the A24 viaducts, in order to bring this strategic stretch of highway up to the latest structural and seismic standards.
The Project at a Glance
- Highway: A24
- Section: L’Aquila West – Tornimparte
- Viaducts: 25
- Project: Demolition and reconstruction of the viaducts
- New structures: Corten steel and concrete
- Seismic protection: state-of-the-art isolators
Why These Projects
The A24 highway crosses an area of the Apennines with high seismic activity. The original structures, designed in the 1960s, are gradually being replaced with new viaducts designed according to the most up-to-date standards for safety, durability, and seismic performance.
The section also reaches elevations exceeding 1,100 meters, where weather conditions are particularly challenging.
What we’re doing
Work is proceeding one lane at a time, so that the highway remains open during the various phases:
- diverting traffic to the opposite lane;
- demolition of existing structures;
- reconstruction of piers and decks;
- installation of seismic reinforcement devices;
- construction of pavement and guardrails;
- testing and reopening to traffic.
Where applicable, old structures are demolished through controlled demolition using micro-charges, in order to reduce construction time; these operations are carried out during brief, scheduled closures, primarily at night.
New earthquake-resistant viaducts
The new decks are constructed using a combination of Corten steel and concrete, making them more durable and flexible than the original structures and compliant with the latest technical building codes.
The new structures are also equipped with seismic isolators, designed to improve the viaduct’s response to the stresses caused by even a strong earthquake.
Status of the work
A map of the route allows you to locate the various viaducts and check their condition:
🟢 Rebuilt and open to traffic
🟡 Work in progress
⚪ Scheduled work
How to Travel During Construction
The highway remains open
Construction is organized by working on one carriageway at a time. Traffic is diverted to the opposite carriageway and managed in both directions to ensure uninterrupted service during reconstruction.
Only certain particularly complex operations, such as controlled demolitions and major deck replacements, require temporary closures. These activities are scheduled primarily at night, when traffic volumes are lower, and are promptly communicated in the “Scheduled Closures” section.