The Special Commissioner for Earthquake Safety and the Restoration of Operations on the A24 and A25 Highways has planned a comprehensive plan of measures to ensure the seismic safety of the network’s priority viaducts.
The program covers 72 viaducts and is divided into 9 sections, which will be implemented progressively according to the identified priorities
The A24 and A25 highways traverse areas characterized by complex topography and high seismic activity. The network includes a particularly large number of bridges, viaducts, and tunnels, many of which were built between the 1960s and 1970s.
Regulatory References
Law No. 228 of 2012 recognized the A24 and A25 highways as strategic infrastructure for Civil Protection purposes and established the need to adapt the network to the safety requirements related to its function and the characteristics of the territories it traverses. Subsequently, Article 206 of Decree-Law No. 34 of 2020 assigned to the Special Commissioner the responsibilities for planning, designing, awarding contracts, and executing the measures necessary to accelerate seismic retrofitting and the restoration of the two highways’ functionality.
The Plan at a Glance
- Highways: A24 and A25
- Viaducts: 72
- Sections: 9
- Objective: structural retrofitting and seismic retrofitting
- Client: Special Commissioner
- Network Management: “strada dei parchi”
This page will be updated gradually as work begins on the various sections.
Section III | A25
Between Marsica and the Peligna Valley
Phase III concerns the seismic retrofitting of 5 pairs of priority viaducts on the A25, with a total length of approximately 2.9 km of deck.
The structures are located in the municipalities of Celano, Pratola Peligna, Roccacasale, and Corfinio, between the Marsica and the Peligna Valley.
The ten viaducts
- Della Foce (East + West), Celano
- Acquaviva (East + West), Pratola Peligna
- Capo Croce (East + West), Pratola Peligna
- Valle dei Fiori (East + West), Pratola Peligna/Roccacasale
- Castellucci (East + West), Roccacasale/Corfinio
What the construction work involves
The work includes:
- demolition and reconstruction of the deck structures;
- retrofitting or reconstruction of the existing piers, depending on the characteristics of each viaduct;
- new steel and concrete deck structures;
- installation of seismic isolators and new expansion joints;
upgrades to flooring and safety systems.
Depending on the nature of the work, demolition will be carried out using mechanical equipment or through controlled demolition with explosives.
Work on the ten viaducts
Della Foce
Mechanical demolition of the existing deck and piers, which will be completely replaced with a new structure.
Acquaviva, Capo Croce, and Valle dei Fiori
Controlled demolition of the deck structures, with structural and seismic reinforcement and retrofitting of the existing piers.
Castellucci Viaduct
Controlled demolition of the deck; the piers and abutments will be completely rebuilt with new foundations on micropiles.
The project also calls for the recovery and reuse of materials resulting from the demolitions
New earthquake-resistant viaducts
The decks will be constructed using composite structures made of Corten steel and concrete and equipped with seismic isolators and next-generation joints.
The solutions adopted are designed to improve safety, durability, and the structures’ response to seismic loads.
Status of the work
🟢 Work completed
🟡 Work in progress
⚪ Scheduled work
How to Travel During Construction
Construction sites are organized so that, during the main phases, one lane remains open to traffic in both directions.
Lane switches and new access points are planned to minimize the length of detours. Operations requiring traffic closures will be concentrated, as much as possible, during nighttime hours and will be announced in a timely manner in Scheduled Closures.